Technical details
The overhead section includes a 6.7 km viaduct. Building the viaduct in an urban area calls on VINCI Construction’s expertise in creating complex engineering structures. The 1,895 segments are prefabricated in the immediate vicinity of the worksite. We have chosen a deck that looks like an inverted “T” with an aeroplane wing profile to refine the edge of the viaduct and create an extremely light architectural design.
Our concrete formulations are designed to quickly build up strength while offering excellent workability. The segments will be placed with a launching gantry. This machine comprises two large metal beams that temporarily rest on the piers already in place, meaning that the gantry can assemble the segments in complete spans.
Self-compacting concrete has been used for the viaduct piers. This type of concrete is injected at the base of the formwork and is able to flow under its own weight, meaning that it can spread throughout the entire height of the formwork (12 metres high) without any need for vibration, which reduces the amount of arduous work for our operatives and produces an excellent quality finish.
A total of 201 piers measuring 9 metres high have been built, supported by 4 piles, with 13 piers on well foundations.